ACTIVITY A. EXCAVATION/STEEL BAR PREPARATION B. FOOTING REBAR INSTALLATION C. POUR CONCRETE FOR FOOTING D. COLUMN BARS/
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
ACTIVITY A. EXCAVATION/STEEL BAR PREPARATION B. FOOTING REBAR INSTALLATION C. POUR CONCRETE FOR FOOTING D. COLUMN BARS/
ACTIVITY A. EXCAVATION/STEEL BAR PREPARATION B. FOOTING REBAR INSTALLATION C. POUR CONCRETE FOR FOOTING D. COLUMN BARS/ FORMWORKS E. POUR CONCRETE FOR COLUMN F. FLOOR/WALL G. ROOF FRAME H. ROOFING I. FINISHING PREDE- CESSOR A B B,C D D E E E.F.H DURATION ES EF LS LF S (DAYS) 2 1 3 3 3 3 3 1 3 REQUIRED: 1. PREDECESSOR DIAGRAM (AON) I 2. FILL UP (ES.EF.LS.LF.S) CHART 3. GANTT CHART 4. INTERPRET RESULT ES= S LS- A GANTT CHART 1 2 3 4 5 6 7 8 9 1 0 D EF= NAME OF ACTIVITY LF- 1 1 1 2 S = LS-ES OR S=LF - EF 1 3 1 4 EF = ES + DURATION (FORWARD PASS) LS LF- DURATION (BACKWARD PASS) 15 1 1 5 6 1 1 78