You are completing a project network diagram with the following information. Task A takes 25 days and has no predecessor

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

You are completing a project network diagram with the following information. Task A takes 25 days and has no predecessor

Post by answerhappygod »

You are completing a project network diagram with the followinginformation. Task A takes 25 days and has no predecessors. Task Bhas a duration of 20 days and has A as its predecessor. Task C canstart when B starts and has a duration of 30 days. Task D can startas soon as B is completed, and has a duration of 10 days. Task Ehas a duration of 40 days and has C and D as its predecessors. Whatis the critical path duration for this network?
Group of answer choices
a. 95 days
b. 45 days
c. 55 days
d. 75 days