You are completing a project network diagram with the followinginformation. Task A takes 25 days and has no predecessors. Task Bhas a duration of 20 days and has A as its predecessor. Task C canstart when B starts and has a duration of 30 days. Task D can startas soon as B is completed, and has a duration of 10 days. Task Ehas a duration of 40 days and has C and D as its predecessors. Whatis the critical path duration for this network?
Group of answer choices
a. 95 days
b. 45 days
c. 55 days
d. 75 days
You are completing a project network diagram with the following information. Task A takes 25 days and has no predecessor
-