The budget at completion for your project is $200,000. The CPIfor your project is 1.25. The project has thus far spent 20% of thebudget. What is the estimate to complete?
Group of answer choices
a. $100,000
b. $120,000
c. $140,000
d. $160,000
The budget at completion for your project is $200,000. The CPI for your project is 1.25. The project has thus far spent
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am