The budget at completion for your project is $200,000. The CPI for your project is 1.25. The project has thus far spent

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The budget at completion for your project is $200,000. The CPI for your project is 1.25. The project has thus far spent

Post by answerhappygod »

The budget at completion for your project is $200,000. The CPIfor your project is 1.25. The project has thus far spent 20% of thebudget. What is the estimate to complete?
Group of answer choices
a. $100,000
b. $120,000
c. $140,000
d. $160,000