Consider a project with the following information. Construct anAON diagram and use the two-pass process algorithm to find ES, EF,LS and LF for each activity.
Activity
Immediate Predecessor
Activity Time
(weeks)
A
-
3
B
A
5
C
A
7
D
B, C
3
E
B
6
F
D,E
4
G
C
2
8. Enter ES and LF of the followingactivities:
ES of activity D is :=____
ES of activity F is :=____
LF of activity G is :=____
LF of activity C is :=_____
9. Enter the slack of the following activities:
The slack time for activity G is :=___
The slack time for activity E is :=___
10. The project length is :=____
11. What is (are) the critical path(s)?
Enter 1, if your answer is A-B-E-F
Enter 2, if your answer is A-B-D-F
Enter 3, if your answer is A-C-D-F
Enter 4, if your answer is A-B-D-F andA-C-G
Enter 5, if your answer is A-B-E-F andA-C-G
Answer := ____