Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to fi

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Consider a project with the following information. Construct an AON diagram and use the two-pass process algorithm to fi

Post by answerhappygod »

Consider a project with the following information. Construct anAON diagram and use the two-pass process algorithm to find ES, EF,LS and LF for each activity.
Activity
Immediate Predecessor
Activity Time
(weeks)
A
-
3
B
A
5
C
A
7
D
B, C
3
E
B
6
F
D,E
4
G
C
2
8. Enter ES and LF of the followingactivities:
ES of activity D is :=____
ES of activity F is :=____
LF of activity G is :=____
LF of activity C is :=_____
9. Enter the slack of the following activities:
The slack time for activity G is :=___
The slack time for activity E is :=___
10. The project length is :=____
11. What is (are) the critical path(s)?
Enter 1, if your answer is A-B-E-F
Enter 2, if your answer is A-B-D-F
Enter 3, if your answer is A-C-D-F
Enter 4, if your answer is A-B-D-F andA-C-G
Enter 5, if your answer is A-B-E-F andA-C-G
Answer := ____