- Tutorial 4 An Hydro Electric Project Has The Following Data Catchment Area A 5x10 M Annual Rainfall F 1 25m M 1 (134.93 KiB) Viewed 37 times
TUTORIAL 4 An hydro-electric project has the following data: Catchment area, A = 5x10⁹ m²; Annual rainfall, F = 1.25m; M
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
TUTORIAL 4 An hydro-electric project has the following data: Catchment area, A = 5x10⁹ m²; Annual rainfall, F = 1.25m; M
TUTORIAL 4 An hydro-electric project has the following data: Catchment area, A = 5x10⁹ m²; Annual rainfall, F = 1.25m; Mean head, H = 30m yield factor, K = 80% Overall efficiency, overall = 70% NB: The yield factor expresses the amount of rainfall that can be utilized since part of the rainfall is lost by evaporation and soil infiltration. 2021/05/19 a) Calculate the annual average power in kW that can be generated [Ans: 32648 kW] b) If the load factor is 40%, determine the rating of generators installed [Ans: 81620 kW]