A construction project requires a concrete mix with proportions of 1.3.2:4.3 as cement, sand, gravel, on a weight basis.
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
A construction project requires a concrete mix with proportions of 1.3.2:4.3 as cement, sand, gravel, on a weight basis.
A construction project requires a concrete mix with proportions of 1.3.2:4.3 as cement, sand, gravel, on a weight basis. The following is available information Determine the water/cement ratio of the concrete mix in gal/sack. Cement content weight per yd' = 4.9 sacks/yd & Specific gravity= 3.2 Sand: SSD with specific gravity (SG) = 2.63 Gravel: SSD with specific gravity (SG) = 2.56 A. 6 B. 8 C. 5 D. 7
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!