A project consists of the following four activities with activity times in days: Activity Predecessor Time A 6 B A 5 C A

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

A project consists of the following four activities with activity times in days: Activity Predecessor Time A 6 B A 5 C A

Post by answerhappygod »

A project consists of the following four activities with
activity times in days:
Activity
Predecessor
Time
A
6
B
A
5
C
A
4
D
B,C
8
Table 9.3
Reference: Ref 9-3
Using Table 9.3, the time to complete the entire project would
be
Select one:
A.
11 days.
B.
19 days.
C.
17 days.
D.
23 days.