A project consists of the following four activities with
activity times in days:
Activity
Predecessor
Time
A
6
B
A
5
C
A
4
D
B,C
8
Table 9.3
Reference: Ref 9-3
Using Table 9.3, the time to complete the entire project would
be
Select one:
A.
11 days.
B.
19 days.
C.
17 days.
D.
23 days.
A project consists of the following four activities with activity times in days: Activity Predecessor Time A 6 B A 5 C A
-