- 7 A Transfer Line With 34 Stations Has An Ideal Cycle Time Of 0 65 Minutes An Average Downtime Of 8 6 Minutes Per Line 1 (12.94 KiB) Viewed 11 times
7. A transfer line with 34 stations has an ideal cycle time of 0.65 minutes, an average downtime of 8.6 minutes per line
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
7. A transfer line with 34 stations has an ideal cycle time of 0.65 minutes, an average downtime of 8.6 minutes per line
7. A transfer line with 34 stations has an ideal cycle time of 0.65 minutes, an average downtime of 8.6 minutes per line stop occurrence, and a station failure frequency of 0.02 for all stations After analysis, the system designer proposes to locate a storage buffor between stations 27 and 28 to improve linc efficiency. Determine: a) The current line efficiency and production rate marks/ b) The maximum possible line efficiency and production rate that would result from installing the proposed storage buffer. 17 marks)