Using the information provided in the table, the network diagram and the project completion time = 25 weeks, calculate t
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Using the information provided in the table, the network diagram and the project completion time = 25 weeks, calculate t
Using the information provided in the table, the network diagram and the project completion time = 25 weeks, calculate the minimum time for completing the project possible. Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Maximum weeks Reduced Crash Cost ($) Activity Crash Cost per Week ($) A 4 500 3 900 1 400 B 4 600 3 700 1 100 C с 6 800 1,300 3 167 D 6 1,500 4 2,150 2 325 E 1.750 4 2.250 N 250 F 5 1,200 5 1,200 0 0 G 6 1,500 4 1,800 2. 150 I 3 500 3 3 500 0 AON network diagram: B H Minimum project completion time = weeks