4 Answer the following questions based on following work planned, completion and actual cost spent in the project. Activ

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

4 Answer the following questions based on following work planned, completion and actual cost spent in the project. Activ

Post by answerhappygod »

4 Answer The Following Questions Based On Following Work Planned Completion And Actual Cost Spent In The Project Activ 1
4 Answer The Following Questions Based On Following Work Planned Completion And Actual Cost Spent In The Project Activ 1 (383.27 KiB) Viewed 74 times
need it asap please
do not copy and paste please
Do good rating
4 Answer the following questions based on following work planned, completion and actual cost spent in the project. Activities Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Total Budget 25% A (Planned %) A (Actual %) 25% 30% 25% 20% 25% 20% $10,000 30% B (Planned %) B (Actual %) 50% 40% 50% 60% $12,000 30% 25% C (Planned %) C (Actual %) 45% 25% $15,000 25% 10% 40% 20% D (Planned %) D (Actual %) 40% 30% $18,000 30% 40% 10% 20% 30% 40% E (Planned %) E (Actual %) $20,000 20% 20% Actual Cost Spent/day $3,000 $9,500 $15,000 $7,500 $5,000 $14,000 NOW
b. Determine the project status (cost overrun or underrun/ schedule ahead or behind) on Day 3. Also determine the cost overrun or underrun % at the end of the project based on the progress made on Day 3. (50 Points)