need it asap please
do not copy and paste please
Do good rating
4 Answer the following questions based on following work planned, completion and actual cost spent in the project. Activities Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Total Budget 25% A (Planned %) A (Actual %) 25% 30% 25% 20% 25% 20% $10,000 30% B (Planned %) B (Actual %) 50% 40% 50% 60% $12,000 30% 25% C (Planned %) C (Actual %) 45% 25% $15,000 25% 10% 40% 20% D (Planned %) D (Actual %) 40% 30% $18,000 30% 40% 10% 20% 30% 40% E (Planned %) E (Actual %) $20,000 20% 20% Actual Cost Spent/day $3,000 $9,500 $15,000 $7,500 $5,000 $14,000 NOW
b. Determine the project status (cost overrun or underrun/ schedule ahead or behind) on Day 3. Also determine the cost overrun or underrun % at the end of the project based on the progress made on Day 3. (50 Points)
4 Answer the following questions based on following work planned, completion and actual cost spent in the project. Activ
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
4 Answer the following questions based on following work planned, completion and actual cost spent in the project. Activ
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!