1 B. Answer the following questions based on the network calculation you solved in Q. No. 1A. b. If Activity L is dela

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

1 B. Answer the following questions based on the network calculation you solved in Q. No. 1A. b. If Activity L is dela

Post by answerhappygod »

1 B Answer The Following Questions Based On The Network Calculation You Solved In Q No 1a B If Activity L Is Dela 1
1 B Answer The Following Questions Based On The Network Calculation You Solved In Q No 1a B If Activity L Is Dela 1 (22.02 KiB) Viewed 54 times
I just need the answer for 1B b. please
need it asap please
do not copy and paste please
Do good rating
1 B. Answer the following questions based on the network calculation you solved in Q. No. 1A.
b. If Activity L is delayed by 5 days, will it delay the total duration of the project and the start date of M, N, and O activities? If yes, then by how many days and why will it delay the total duration and the start date of those activities? Show the calculations. Give the specific reasons for your answers (25 Points)
1. A. Conduct forward and backward pass and determine ES, EF, LS, LF, TF, and FF for the following network. Also identify the critical activities and critical paths. No need fill out the table. However, for Part B, it is required to show the FF calculations. (50 Points) ES EF Activity (Dur) LS TF FF LF A (2) D (7) G(3) J (7) M (3) B (1) E (6) H(7) K(5) N (5) C(2) F(3) 1(8) L (3) 0(3)