1 B. Answer the following questions based on the network calculation you solved in Q. No. 1A.
b. If Activity L is delayed by 5 days, will it delay the total duration of the project and the start date of M, N, and O activities? If yes, then by how many days and why will it delay the total duration and the start date of those activities? Show the calculations. Give the specific reasons for your answers (25 Points)
1. A. Conduct forward and backward pass and determine ES, EF, LS, LF, TF, and FF for the following network. Also identify the critical activities and critical paths. No need fill out the table. However, for Part B, it is required to show the FF calculations. (50 Points) ES EF Activity (Dur) LS TF FF LF A (2) D (7) G(3) J (7) M (3) B (1) E (6) H(7) K(5) N (5) C(2) F(3) 1(8) L (3) 0(3)
1 B. Answer the following questions based on the network calculation you solved in Q. No. 1A. b. If Activity L is dela
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
1 B. Answer the following questions based on the network calculation you solved in Q. No. 1A. b. If Activity L is dela
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!