The network diagram of a construction project is shown below with its three time estimates of each activity. Determine - (i) The critical path and its standard deviation. (ii) Probability of completing the project in 40 days. (ii) The time duration at which 95% of the project work is likely to be completed 17 17 31 31 35 35 (3.5,13) (2, 4, 6) 7 0 0 1 5 5 (2,5,8) (8, 11, 20) 2 3 (4,7,16) 4.9, 20 5 17 17 (7, 10, 13) 3, 7, 17 15 19 2, 3, 10 27 27