QUESTION 3 a) b) c) Define resource loading. i) List TWO (2) principles in crashing a project. Given the following proje

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

QUESTION 3 a) b) c) Define resource loading. i) List TWO (2) principles in crashing a project. Given the following proje

Post by answerhappygod »

Question 3 A B C Define Resource Loading I List Two 2 Principles In Crashing A Project Given The Following Proje 1
Question 3 A B C Define Resource Loading I List Two 2 Principles In Crashing A Project Given The Following Proje 1 (44.19 KiB) Viewed 11 times
QUESTION 3 a) b) c) Define resource loading. i) List TWO (2) principles in crashing a project. Given the following project P in Table 2. Determine the following: Activity A ii) B C D E F G I Predecessor B A, C A, C B D E, F Normal Duration (day) 5 7 2 3 00 8 5 6 the critical path and time. Table 2 the slope for each activity. Normal cost (S) 60 40 50 20 40 80 50 60 Crash Duration (day) 3 2 6 1 5 3 [14 marks] [1 marks] [2 marks] Crash cost (S) 150 200 160 50 290 100 180 [3 marks] [8 marks]