QUESTION 3 a) b) c) Define resource loading. i) List TWO (2) principles in crashing a project. Given the following proje
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
QUESTION 3 a) b) c) Define resource loading. i) List TWO (2) principles in crashing a project. Given the following proje
QUESTION 3 a) b) c) Define resource loading. i) List TWO (2) principles in crashing a project. Given the following project P in Table 2. Determine the following: Activity A ii) B C D E F G I Predecessor B A, C A, C B D E, F Normal Duration (day) 5 7 2 3 00 8 5 6 the critical path and time. Table 2 the slope for each activity. Normal cost (S) 60 40 50 20 40 80 50 60 Crash Duration (day) 3 2 6 1 5 3 [14 marks] [1 marks] [2 marks] Crash cost (S) 150 200 160 50 290 100 180 [3 marks] [8 marks]