An activity has a planned duration of 10 days and a float of 5 days, after updating the schedule it was found that it ha
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
An activity has a planned duration of 10 days and a float of 5 days, after updating the schedule it was found that it ha
An activity has a planned duration of 10 days and a float of 5 days, after updating the schedule it was found that it has started as scheduled, the elapsed duration is 7 days until the current data date and the remaining duration is 7 days. What could be the current float of the activity? (3/3 Points)
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!