1. Draw an AON network of this project.
2. Identify ES, EF, LS, LF times of this project network.
3. What is the project duration?
4. What is the optimal way to cut the project duration by 1 day?
What is the project cost then?
blackboard.h attps:... Bb https:... Goog... Big P... Stake... tutor... 15. Given the following project (all times are in days): Pre- decessor Activity Crash Crash Time Cost a с Normal Normal Time Cost 5 $50 4 40 7 70 2 20 3 30 80 50 60 $150 200 160 50 d а, с au bo w Nou e a, c b wael-anw 8 g d e, 290 100 180