PROBLEM #1 a. Using a waste factor of 8 percent, determine the number of cubic yards of concrete needed to pour the cont
Posted: Wed Apr 27, 2022 2:57 pm
PROBLEM #1 a. Using a waste factor of 8 percent, determine the number of cubic yards of concrete needed to pour the continuous footing shown in figure 1 and 2 below. Assume that the wall is centered over the footing. b. Determine the amount of rebar needed for the continuous footings shown in figure 1 and 2 below. Allow for 2 inches of cover and extend the dowels 15 inches into the wall. Add 10 % for lap and waste to the continuous bars. Figure 1: Foundation Plan HREBARQ OC BOTH WAYS 12 $S DONELSO OC ALTERNATING DIRECTIONS REBAR @roc 13 BEACH CONT REBAR Figure 2: Foundation Section