The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: Activity
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: Activity
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: Activity Activity Time (days) Immediate Predecessor(s) 1 4 3 B с D E F G A А B, C D E E 5 2 5 a. Choose the correct network diagram for this project. OA @ Q @ Start- OC. @ D. @ Q Start - - Finch b. Determine the critical path and project duration The critical path is path A-C-D-E and the project duration is 24 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Slack Activity (days) A B C D OMODODO E F G