Example 14.3: Consider the Gross Requirements for A as specified below. Item Lead Time (LT) Lot Size On Hand (O/H) A 1 W
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Example 14.3: Consider the Gross Requirements for A as specified below. Item Lead Time (LT) Lot Size On Hand (O/H) A 1 W
Example 14.3: Consider the Gross Requirements for A as specified below. Item Lead Time (LT) Lot Size On Hand (O/H) A 1 Week 25 25 Scheduled Receipts (S/R) 25 Week 4 B (2) 1 Week 50 B(2) 50 Week 1 & 4 50 C(2) C (2) 1 Week 100 100 200 Week 2 D (2) 1 Week 100 1000 0 D(2) D(2) Item: LT: Lot Sizing 1 2 3 4 5 Item: LT: Lot Sizing 1 2 3 4 5 Gross Requirements 20 40 45 65 150 Gross Requirements Scheduled Receipts Scheduled Receipts Projected on Hand Projected on Hand Net Requirements Net Requirements Planned Order Receipts Planned Order Receipts Planned Order Releases Planned Order Releases Item: LT: Lot Sizing 2 3 5 Item: LT: Lot Sizing 1 2 3 4 5 Gross Requirements Gross Requirements Scheduled Receipts Scheduled Receipts Projected on Hand Projected on Hand Net Requirements Net Requirements Planned Order Receipts Planned Order Receipts Planned Order Releases Planned Order Releases
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!