You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone.
What is the project's schedule performance index?
A. 1.06
B. 0.92
C. -$37,800
D. 0.93
You are the project manager of the NNH Project. In this project you have created a contingency response that the schedul
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
You are the project manager of the NNH Project. In this project you have created a contingency response that the schedul
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!