Your organization is trying to determine which one of two opportunities they will pursue. The Project A is worth $235,98

Posted: Thu Aug 18, 2022 8:11 am
by answerhappygod
Your organization is trying to determine which one of two opportunities they will pursue. The Project A is worth $235,987 and Project B is worth $567,000 but carries significant risk. The organization elects to purse Project B and not Project A.
What is the opportunity cost in this scenario?

A. $331013
B. There is not enough information to know as the risk for Project B has not been quantified.
C. $235,987
D. $567,000