Your organization is trying to determine which one of two opportunities they will pursue. The Project A is worth $235,987 and Project B is worth $567,000 but carries significant risk. The organization elects to purse Project B and not Project A.
What is the opportunity cost in this scenario?
A. $331013
B. There is not enough information to know as the risk for Project B has not been quantified.