You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set

Post by answerhappygod »

You are a project manager for an organization that uses Project Server 2013. You have the appropriate permissions to set all baselines. Your project experiences a scope change, which requires you to add tasks to the end of the schedule.You need to retain historical information for both completed and in-progress tasks but create a baseline that includes the newly-selected tasks.You check out your schedule in Project Web App (PWA) for editing and select the newly- added tasks.What should you do next?

A. Set an interim plan.
B. Use an unused baseline to set a new baseline.
C. Clear the baseline and then set a baseline for the entire project.
D. Set a baseline for only the selected tasks.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply