Your company uses Project Professional 2013, and you are setting up an initial planning schedule.You need to set each task duration as estimated, until the estimate is confirmed by the assigned resource.What should you do?
A. Select the estimated check box.
B. Use a task custom field and set the Roll task down to assignment check box.
C. Enter the duration suffixed with -ed for estimated days.
D. Set the task to manually scheduled. E. Use an assignment custom field and set the Roll assignment up to task check box.