Your company uses Project Professional 2013.You are building a schedule by using predecessors to help determine a logica

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Your company uses Project Professional 2013.You are building a schedule by using predecessors to help determine a logica

Post by answerhappygod »

Your company uses Project Professional 2013.You are building a schedule by using predecessors to help determine a logical duration.The following image shows a baselined list of tasks with predecessors:You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule.You need to determine what the results are to the schedule when inactivating Task C.How should you answer?
Your Company Us 1
Your Company Us 1 (228.31 KiB) Viewed 65 times
A. The finish date is reduced by four working days, cost remains unchanged, and baseline cost is reduced by $400.
B. The finish date is reduced by five working days, cost remains unchanged, and baseline cost is unchanged.
C. The finish date is reduced by six working days, cost is reduced by $400, and baseline cost is reduced by $400.
D. The finish date is reduced by four calendar days, cost is reduced by $400, and baseline cost is reduced by $400. E. The finish date is reduced by six calendar days, cost is reduced by $400, and baseline cost is unchanged.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply