You are a project manager who uses Project Professional 2013.After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled dates.You need a graphical view that shows the current schedule to baseline.Which view should you use?
A. Detail Gantt view
B. Tracking Gantt view
C. Leveling Gantt view
D. Gantt Chart view