You are a project manager who uses Project Professional 2013.After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled dates.You need a graphical view that shows the current schedule to baseline.Which view should you use?
A. Detail Gantt view
B. Tracking Gantt view
C. Leveling Gantt view
D. Gantt Chart view
You are a project manager who uses Project Professional 2013.After updating a project schedule, you want to determine th
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
You are a project manager who uses Project Professional 2013.After updating a project schedule, you want to determine th
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!