You are a project manager for an organization that uses Project Professional 2013.You are planning a project schedule that starts on March 1 and lasts four months.However, the sponsor now asks that the project be delayed to have a finish date ofDecember 31.
A. Change all task constraint types to Start no later than.
B. Change the Schedule from field to Project Finish Date.
C. Change the project Start date so that the project will finish on December 31.
D. Change all task constraint types to As late as possible. E. Change the project Finish date so that the project will finish on December 31.
You are a project manager for an organization that uses Project Professional 2013.You are planning a project schedule th
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
You are a project manager for an organization that uses Project Professional 2013.You are planning a project schedule th
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!