Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

You are the project manager of project for a client. The client has promised your company a bonus, if the project is com

Post by answerhappygod »

You are the project manager of project for a client. The client has promised your company a bonus, if the project is completed early. After studying the project work, you elect to crash the project in order to realize the early end date. This is an example of what type of risk response?

A. Negative risk response, because crashing will add risks.
B. Positive risk response, as crashing is an example of enhancing.
C. Positive risk response, as crashing is an example of exploiting.
D. Negative risk response, because crashing will add costs.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!

This topic has 1 reply

You must be a registered member and logged in to view the replies in this topic.


Register Login
 
Post Reply