When reviewing a backbone distribution system within a building provided to you for standards compliance, you see that there are several cables with bridge taps built in. Which one of the following options is correct?
A. Ensure all cables meet maximum lengths to ensure standards compliance
B. Ensure all cables exceed minimum cable lengths to avoid NEXT(near-end crosstalk)
C. Provide recommendations to remove all bridge taps
D. Provide recommendations to remove one bridge tap per cable
E. Do nothing as the design will pass all design parameters