Which describes the 'Implement' step within the recommended risk management procedure?
A. Project Support will allocate the risk budget to fund the selected risk responses
B. The risk owner will decide the best response to control the risk
C. The risk owner and the risk actioner will carry out activities to control and deal with the risk
D. The Project Manager will formulate the Risk Management Strategy
Which describes the 'Implement' step within the recommended risk management procedure?
-