Q2) Use the information in the table: Late Finish Predecessor Task A B с D E F A A C, B с D, E Early Early Late Duration
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Q2) Use the information in the table: Late Finish Predecessor Task A B с D E F A A C, B с D, E Early Early Late Duration
Q2) Use the information in the table: Late Finish Predecessor Task A B с D E F A A C, B с D, E Early Early Late Duration Start Finish Start 8 14 23 8 6 23 26 32 32 38 a) Determine the late start time for Activity E? b) Determine the early start time for Activity B? c) Determine the early finish time for Activity D? d) Determine the late finish time for Activity B? e) Which activities are on the critical path?