The Below table shows list of activities for a small project with the predecessors and duration for each activity. The p

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

The Below table shows list of activities for a small project with the predecessors and duration for each activity. The p

Post by answerhappygod »

The Below Table Shows List Of Activities For A Small Project With The Predecessors And Duration For Each Activity The P 1
The Below Table Shows List Of Activities For A Small Project With The Predecessors And Duration For Each Activity The P 1 (184.12 KiB) Viewed 26 times
just solve Q 5,6,7,8
subject construction manegment
The Below table shows list of activities for a small project with the predecessors and duration for each activity. The project started on (2nd May 2022). There are five (5) working days in a week. No works required during the weekend (Saturday and Sunday) and public holidays. Note: there is a public holiday on 9th May, 2022. 1. Based on the information given develop a network diagram using Activity on Node (AON) method. 2. Calculate the ES, EF, LS, LF for each activity on the diagram? 3. What is the critical path of the project? 4. List all the project activities in a table including the ES, LS, EF, LF, FF, TF as a number? 5. List all the project activities in a table including their dates of ES, LS, EF, LF? 6. Draw the Gantt chart for all the activities by Microsoft Excel using date and another Gantt chart using numbers? 7. What is the total project duration? 8. What is the project completion date? ACTIVITY PREDECESSOR DURATION (days) 0 7 6 START START START START Clear & Grub Order & Delivery Reinforcement Order & Delivery PC Slabs Excavate Footings and Utilities Delivery Frames, Channel etc RC Footings Form Footings Masonry & Bearing Walls Erect Joists and Deck Foundation Block Backfill FINISH 5 6 9 10 8 3 Clean & Grub Clean & Grub Order & Delivery Reinforcement Excavate Footings and Utilities (SS+2) Order & Delivery PC Slabs, RC Footings (FF +2) Masonry & Bearing Walls Delivery Frames, Channel etc, RC Footings (FS+4) Form Footings, Foundation Block Erect Joists and Deck, Backfill 7 11 9 0
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!
Post Reply