A project manager wants to compress her project schedule (week). She should compress one time unit (week) per move to re

Posted: Tue Apr 26, 2022 12:34 pm
by answerhappygod
A project manager wants to compress her project schedule (week).
She should compress one time unit (week) per move to reduce the
project schedule. The total indirect cost for the project is $2,000
and there is a savings of $100 per time unit reduced.
A Project Manager Wants To Compress Her Project Schedule Week She Should Compress One Time Unit Week Per Move To Re 1
A Project Manager Wants To Compress Her Project Schedule Week She Should Compress One Time Unit Week Per Move To Re 1 (15.53 KiB) Viewed 57 times
Activity Crash Cost Wax Crash Time Normal Time Normal Cost A 0 0 2 200 B 50 1 4 1000 C 200 2 5 800 D 100 1 5 1000 E 200 2 5 1000 F 100 1 3 800 G 40 1 5 1000 H 40 1 4 1000 | 0 0 1 200 5 A B 員 目 目 目 目 2 4 5 3 E H 5 4
Answer following questions regarding the project time reduction by 2 weeks (from 20 weeks to 18 weeks). Question 7 (6 points) What is the project total cost (direct + indirect) when she has reduced the project duration from 20 to 19 weeks? $8,750 $8,340 8,950 $9,140 $8,400
Question 8 (6 points) What is the project direct cost when she has reduced the project duration from 20 to 19 weeks? $7,100 $7,200 $7,050 $7,400 $7,300