A project manager wants to compress her project schedule (week).
She should compress one time unit (week) per move to reduce the
project schedule. The total indirect cost for the project is $2,000
and there is a savings of $100 per time unit reduced.
Activity Crash Cost Wax Crash Time Normal Time Normal Cost A 0 0 2 200 B 50 1 4 1000 C 200 2 5 800 D 100 1 5 1000 E 200 2 5 1000 F 100 1 3 800 G 40 1 5 1000 H 40 1 4 1000 | 0 0 1 200 5 A B 員 目 目 目 目 2 4 5 3 E H 5 4
Answer following questions regarding the project time reduction by 2 weeks (from 20 weeks to 18 weeks). Question 7 (6 points) What is the project total cost (direct + indirect) when she has reduced the project duration from 20 to 19 weeks? $8,750 $8,340 8,950 $9,140 $8,400
Question 8 (6 points) What is the project direct cost when she has reduced the project duration from 20 to 19 weeks? $7,100 $7,200 $7,050 $7,400 $7,300
A project manager wants to compress her project schedule (week). She should compress one time unit (week) per move to re
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
A project manager wants to compress her project schedule (week). She should compress one time unit (week) per move to re
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!