Project Time Reduction A project manager wants to compress her project schedule (week). She should compress one time unit (week) per move to reduce the project schedule until she reach the has crashed point of the network. The total indirect cost for the project is $2,000 and there is a savings of $100 per time unit reduced. Activity Crash Cost Max Crash Time Normal Time Normal Cost 0 0 2 200 A B 50 1 4 1000 С 200 2 5 800 D 100 1 5 1000 E 200 2 5 1000 F 100 1 3 800 G 40 1 5 1000 H 40 1 4 1000 1 0 0 1 200 с 5 5 同 B 漫画 А B E H 2 3 D G 5
What is the project direct cost when she has reduced the project duration from 19 to 18 weeks? $7,340 $7,400 $7,150 $7,250 $7,440
What is the project direct cost when she has reduced the project duration from 20 to 19 weeks? $7,200 $7,300 $7,100 $7,050 $7,400
Project Time Reduction A project manager wants to compress her project schedule (week). She should compress one time uni
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Project Time Reduction A project manager wants to compress her project schedule (week). She should compress one time uni
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!