You have been asked to calculate the discounted payback period of the following project. The project has a cost of $215,
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
You have been asked to calculate the discounted payback period of the following project. The project has a cost of $215,
You have been asked to calculate the discounted payback period of the following project. The project has a cost of $215,000. The project has an expected cash flow of $102,000 in year 1, an expected cash flow of $72,000 in year 2, an expected cash flow of $82,000 in year 3 and an expected cash flow of $92,000 in year 4. The required rate of return is 6% compounded annually. How many years does it take for the project to recover its cost on a discounted basis? (What is the discounted payback period in years?) 2.65 02.96 02.62 02.79