If a project is over budget and the contractor suggest using
less efficient, but still code compliant HVAC equipment as a means
of reducing cost; this would be an example of value
engineering.
True
False
If a project is over budget and the contractor suggest using less efficient, but still code compliant HVAC equipment as
-