Problem Solving. Show your detailed solution. 1. From the figure below, estimate the time required for each activity, de

Posted: Mon Apr 25, 2022 9:01 am
by answerhappygod
Problem Solving Show Your Detailed Solution 1 From The Figure Below Estimate The Time Required For Each Activity De 1
Problem Solving Show Your Detailed Solution 1 From The Figure Below Estimate The Time Required For Each Activity De 1 (54.09 KiB) Viewed 44 times
Problem Solving. Show your detailed solution. 1. From the figure below, estimate the time required for each activity, determine the critical time and update the pert chart ACTIVITY DESCRIPTION PRECEDENCE <UA A B с D E F G 18 INITIAL DESIGN SURVEY MARKET BUILD PROTOTYPE TEST PROTOTYOE REDESIGNING MARKET TESTING SET UP PRODUCTION OPTIMISTIC MOST PESSIMISTIC EX TIME LIKELY TIME DL TIME 12 16 26 6 9 18 8 10 2 3 4 3 4 11 6 8 10 15 20 25 A A с BD E F 2 A-17 B-10 15 18 H G-20 2 5 6 C-11 D-3 3