An engineer conducted a site visit to a particular treatment plant. A measurement on the sedimentation tank is made in o
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
An engineer conducted a site visit to a particular treatment plant. A measurement on the sedimentation tank is made in o
An engineer conducted a site visit to a particular treatmentplant. A measurement on the sedimentation tank is made in order toestimate the flow rate. The ratio of the depth of water to thewidth of the tank is 1:1.64, and the ratio of the width to thelength of the tank is 1:4. The surface loading, which is in m/day,is 0.30 times the surface area of the tank. The width of the tankis 4.1 m. Determine the dimension of the tank, the length of outletweir and its flow rate