Please Solve all of the three subquestions
You have been hired as the junior engineer for a bus shelter construction project for Stark Construction Ltd. After brainstorming with your team, a three point estimation was used to approximate the durations of the project activities. Consider the following activity table with three point time estimates for the project. All durations are given in days. Task ID Predecessor Likely duration A B с D E F G H 1 J K L M A,B C D E,D F F G,H | J,K L Optimistic duration 2 4 3 1 2 5 8 6 9 5 5 7 3 3 6 4 2 3 7 12 8 11 7 6 8 5 b.) Find the critical path and mean duration of the project. Pessimistic duration c.) Evaluate the probability of completing the project in 57 days. 6 8 5 5 5 8 14 10 12 Using your skills in project management and scheduling, you are required to: a.) Create a suitable network diagram from the tasks in the activity table. 8 7 10 7 E
Please Solve all of the three subquestions
-