All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified inter

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified inter

Post by answerhappygod »

All Projects A To G Are 7 Year Projects Npv Net Present Value Irr Internal Rate Of Return Mirr Modified Inter 1
All Projects A To G Are 7 Year Projects Npv Net Present Value Irr Internal Rate Of Return Mirr Modified Inter 1 (59.06 KiB) Viewed 24 times
Question 1 options:
If projects A & B are mutually exclusive, projects C and Dare also mutually exclusive and projects F and G are also mutuallyexclusive (all others are independent), under the PI rule projectsB, C, and G should be undertaken
If projects A & B are mutually exclusive, projects C and Dare also mutually exclusive and projects F and G are also mutuallyexclusive (all others are independent), under the MIRR ruleprojects B, C, and F should be undertaken
If all projects are mutually exclusive, under the NPV rule onlyproject B should be taken
If all projects are independent, under the NPV rule, onlyproject E should be rejected
If projects A & B are mutually exclusive, projects C and Dare also mutually exclusive and projects F and G are also mutuallyexclusive (all others are independent), under the NPV rule projectsB, C, and G should be undertaken
If all projects are mutually exclusive, under the NPV ruleprojects A, B, C, D, F and G should be taken
If all projects are independent, under the PI rule, projects A,B, C, D, F, and G should be taken
If projects A & B are mutually exclusive, projects C and Dare also mutually exclusive and projects F and G are also mutuallyexclusive (all others are independent), under the IRR rule projectsB, C, and G should be undertaken
If all projects are independent, under the MIRR rule onlyproject E should be rejected
If all projects are independent, under the IRR rule onlyprojects A, B, C, D, F and G should be taken
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria NPV= IRR= MIRR= PI= The cost of capital (r) is 10%. Project A $14,154 28.66% 17.28% 1.57 Project_B Project_C Project_D_ Project_E $77,992 $29,515 $11,564 ($8,849) 20.33% 19.72% 45.52% 9.03% 14.35% 12.86% 22.76% 1.31 1.20 2.16 9.53% 0.97