Six sites have been identified for a parking lot in downtown Blacksburg. Because the sites are plots of land, their salv

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Six sites have been identified for a parking lot in downtown Blacksburg. Because the sites are plots of land, their salv

Post by answerhappygod »

Six Sites Have Been Identified For A Parking Lot In Downtown Blacksburg Because The Sites Are Plots Of Land Their Salv 1
Six Sites Have Been Identified For A Parking Lot In Downtown Blacksburg Because The Sites Are Plots Of Land Their Salv 1 (30.09 KiB) Viewed 15 times
Six Sites Have Been Identified For A Parking Lot In Downtown Blacksburg Because The Sites Are Plots Of Land Their Salv 2
Six Sites Have Been Identified For A Parking Lot In Downtown Blacksburg Because The Sites Are Plots Of Land Their Salv 2 (29.69 KiB) Viewed 15 times
Six Sites Have Been Identified For A Parking Lot In Downtown Blacksburg Because The Sites Are Plots Of Land Their Salv 3
Six Sites Have Been Identified For A Parking Lot In Downtown Blacksburg Because The Sites Are Plots Of Land Their Salv 3 (101.11 KiB) Viewed 15 times
Six sites have been identified for a parking lot in downtown Blacksburg. Because the sites are plots of land, their salvage value and investment cost are identical. A 10-year study period has been specified, and the MARR is 19% per year. Which site should be chosen based on the IRR criterion? Click the icon to view the alternatives description.

Investment cost (thousands) Annual revenue minus expense (thousands) IRR on total investment A $80 $13 16.2% B $130 $40.5 31.2% с $230 $58 25.2% D $370 $100.5 27.2% E $470 $120.5 25.6% F $730 $150.5 20.6%

Which alternative would you choose as a base one? Choose the correct answer below. Alternative E Alternative C Alternative A Alternative F Alternative D Alternative B Analyze the difference between the base alternative and the second-choice alternative. IRR A( %. (Round to one decimal place.) Analyze the difference between the current base alternative and the third-choice alternative. %. (Round to one decimal place.) IRR A( ) = 1 Analyze the difference between the current base alternative and the fourth-choice alternative. %. (Round to one decimal place.) IRR A( - Analyze the difference between the current base alternative and the fifth-choice alternative. The IRR A( %. (Round to one decimal place.) 0 0 0 0 Which alternative should be selected? Choose the correct answer below. A. Alternative C B. Alternative E C. Alternative F D. Alternative B O E. Alternative A F. Alternative D
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!