mi c 60 (25pts) 0.2 Study the table below for a project that must be completed in 15 working days and answer to the foll
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
mi c 60 (25pts) 0.2 Study the table below for a project that must be completed in 15 working days and answer to the foll
questions The project starts on May 20, 2022. Activit Pre Expecte Varian Name # of Norm Cras Cras Actual Assume: d. d time of Laborld h h Cost % (day) labor ay Cost Time Cost (No completi initial (S) (day) (S) crashin on at S g) day 6) A 3 1.78 AM 2 50 2 100 70 100 B 3 0.00 X, L. 7 40 1 40 40 100 NK, O, P. w A 3 4.00 A, M. 4 70 2 160 100 J.G D A 4 2.75 P. W. 3 20 2 50 50 100 2 E B 4 0.45 A.M. 2 30 3 60 50 100 F B 5 1.45 J.G 5 30 2 330 30 60 W.Z. V G CF 3 0.00 AN 6 1 100 20 20 K, X VG H G 3 0.36 W, 0. 60 100 J.A. х SO 5 N 0 a. Draw the network and the Gantt chart using MS project. Write the network down on paper. [4pts) b. Add a project summary task, what is the duration of the project? [1 pts] c. Identify all paths and highlight the C.P.2 [2pts] d. Add the resources to each activities. Do you have overallocated resources. Level the project [3pts) e. Based on the labor load of the project (without crashing), level the labor resources of this project manually. Compare with part d. Is the labor load better? Why? [4pts] f. Calculate the project EV. [2pts] g. Calculate the project CPI. [2pts] h. Find the probability that the project will be completed in 11 days (without crashing). Comment on the result. Project variance = 3. [2pts) i. Calculate the crash cost-per-day (all activities may be partially crashed). [1 pt) j. Perform all possible crashes on the activities. What is the duration after crashing? What will the project cost? [4pts]
mi c 60 (25pts) 0.2 Study the table below for a project that must be completed in 15 working days and answer to the following